Drax Adds Rail Link
A one-year-old rail link has increased capacity to deliver more sustainable biomass from Drax’s LaSalle BioEnergy pellet plant in Urania, La., to its UK power station. The $15 million rail link, combined with other initiatives, have already contributed to a $5/tonne reduction in Drax’s biomass production costs in 2019.
The five miles of rail track connects Drax’s LaSalle BioEnergy pellet plant to the regional rail network, enabling freight trains to deliver the pellets to the company’s dedicated export facility at the Port of Greater Baton Rouge. The addition of the rail link has allowed Drax to deliver around 7,000 tonnes of sustainable biomass to the Port of Greater Baton Rouge in each train, compared to just 27 tonnes that could be transported by each truck previously.
A team of close to 40 contractors worked through two of the wettest Louisiana winters in decades to clear the site, excavating around 180,000 cubic yards of dirt to level off the ground and stabilize it before three sets of rail tracks could be laid. The work also included installing conveyors to get the pellets to the new rail loading point.
The rail link was commissioned last May and is now fully operational—and is part of Drax’s wider efforts to cut the costs of its biomass by around a third by 2027.
RELATED ARTICLES:
Drax Announces $40M Investment In Arkansas
Drax Sets Sights On Carbon Capture
Pinnacle Renewable Energy To Be Acquired By Drax Group
Earthworm, Drax Working Together
Latest news
Key Committee Boosts Biomass Before Fall EU Parliament Vote
Working on the EU’s upcoming Renewable Energy Directive III (REDIII) that will update the Union’s renewable energy policies, the EU Parliament’s Industry Research and Energy (ITRE) Committee recently voted to not only uphold policies that treat wood pellets as carbon neutral, but also expand the use of wood pellets as a coal substitute…
Wood Bio Conference Speaker Pete Madden: “This is going to be an incredible decade for our sector.”
Going into the seventh Wood Bioenergy Conference & Expo, organizers said the lineup of keynote speakers, on paper, was the best in the history of the event. The real thing was even better. Speakers from their wide-ranging perspectives provided a crystal clear picture of how the wood-based energy shapes up today and what to expect moving forward…
B&W Enters Kiewit, Fidelis Biomass Project
Babcock & Wilcox is partnering with Kiewit Industrial to deliver Fidelis New Energy’s planned net-negative carbon impact biomass power plant at the Port of Greater Baton Rouge, La. The 200 MW electricity plant will be the largest of its kind in the world, according to the participants…
Find Us On Social
Subscribe to Our Newsletter
Wood Bioenergy News Online hits the inboxes of subscribers in the wood-to-energy sectors.
Subscribe/Renew
Wood Bioenergy is published and delivered worldwide 6 times per year. Free to qualified readers in the U.S. Subscribers outside the U.S. are asked to pay a small fee.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative.