Enviva Gears Up For Lucedale Plant

Enviva reports that in July the Mississippi Department of Environmental Quality Permit Board unanimously approved the air permit for the proposed wood pellet plant in Lucedale, Miss., which is the principal permit required to begin construction.

In addition, Enviva continues to evaluate a potential wood pellet production plant in Epes, Alabama, along with other sites in Alabama and Mississippi, which would export wood pellets through the Pascagoula terminal.

Enviva reports that its industrial wood pellet plant in Hamlet, NC plant is now operating and expects to exit 2019 with a production run-rate of 500,000 MTPY and will reach its nameplate production capacity of 600,000 MTPY in 2021.

Enviva announced that projects to increase the aggregate production capacity of its wood pellet production plants in Northampton, North Carolina and Southampton, Virginia by approximately 400,000 MTPY are progressing, as detailed engineering is in process, major pieces of equipment are being delivered, and site preparation work is advancing. Enviva expects to complete the construction of the expansion activities in the first half of 2020 with startup thereafter, subject to receiving necessary permits.

RELATED ARTICLES:

UK Biomass Demand Rises; Enviva Reports New Japanese Contract

Enviva Considers Biomass Role In Hydrogen Economy

Finite Carbon Receives New Majority Stakeholder

Enviva, Finite Carbon Focus On Small Landowners

Enviva Reports On New Pellet Projects

Enviva Announces Acquisitions

Enviva Publishes Paper, Hosts Webinar

Enviva Pellet Plant Receives Thumbs Up

Latest news

Tigercat Triangulated Harvesting Head

Tigercat Triangulated Harvesting Head   In late September 2023, visitors to the Pacific Logging Congress live demo event held in Washington got a sneak peak of the new Tigercat 573 harvesting head processing logs on the end of a Tigercat 875E logger. Since then,...

Titan Upgrades Tire Manufacturing Facility

Titan Upgrades Tire Manufacturing Facility Titan International (Titan) has completed a major upgrade to its manufacturing facility in Des Moines, Ia. The $2 million investment is part of Titan’s multi-year strategic capital plan and includes the addition of two new...

Major Carbon Offset Project License Revoked

Major Carbon Offset Project License RevokedEnvironmental officials in Indonesia recently revoked the license of one of the world’s largest carbon offsets projects, claiming the license-holder, PT Rimba Raya Conservation, transferred its license to a third-party...

Find Us On Social

Subscribe to Our Newsletter

Wood Bioenergy News Online hits the inboxes of subscribers in the wood-to-energy sectors.

Subscribe/Renew

Wood Bioenergy is published and delivered worldwide 6 times per year. Free to qualified readers in the U.S. Subscribers outside the U.S. are asked to pay a small fee.

Advertise

Complete the online form so we can direct you to the appropriate Sales Representative.