Hybrid Solar-Biomass Plant Is Running

Two 20.5 MW heaters manufactured by Sugimat for Termosolar Borges, the world’s first solar thermal-biomass hybrid plant, are operating at full capacity after successful performance tests. The plant, unique in the world due to its process conditions, is the first to combine biomass and thermosolar energy through a field of parabolic trough mirrors. Thanks to this hybridization, the plant, located in Les Borges Blanques (Lleida, Spain), provides energy 24 hours a day. In addition to the heaters, Sugimat developed the remainder of the plant’s elements in turnkey mode.
Having successfully passed the performance tests, both heaters, fed with woody biomass and with a power of 20.5 MW, are now working in hybrid mode with a field of parabolic trough solar receivers up to 390ºC.
In addition to the boilers, Sugimat developed the heat recovery systems, integral control system and emission treatment.
Hybridization of thermal solar energy with biomass increases the plant’s operating time to 150%. In this way, an unmanageable energy asset such as a solar concentration plant is transformed into a manageable one, given that the plant can continue to produce electricity at night or on days without sun. Manageable plants with renewable energy are those required to carry out the decarbonization process, complementing the strong input of photovoltaic and wind power, thus guaranteeing the stability of the system and the balance between generation and consumption.
Latest news
Enviva Publishes Paper, Hosts Webinar
On May 27, Jennifer Jenkins, Vice President and Chief Sustainability Officer, Enviva, and Roger Ballentine, President, Green Strategies, hosted a webinar based on a paper the two published May 6 called Seeing The Forest: Sustainable Wood Bioenergy In The Southeast U.S. The hour and a half long presentation touched on the major topics of the paper, while also including a question and answer portion from participants…
KPA Unicon Delivers Boiler Plant
The bio-heating boiler plant delivered for Fortum to Espoo, Finland, in the Helsinki metropolitan area, was handed over for commercial use on May 5, 2020. Unicon Renefluid bubbling fluidized bed (BFB) boiler…
Drax Adds Rail Link
A one-year-old rail link has increased capacity to deliver more sustainable biomass from Drax’s LaSalle BioEnergy pellet plant in Urania, La., to its UK power station. The $15 million rail link, combined with other initiatives, have already contributed to a $5/tonne reduction in Drax’s biomass production costs in 2019. The five miles of rail track connects Drax’s LaSalle BioEnergy pellet plant…
Find Us On Social
Subscribe to Our Newsletter
Wood Bioenergy News Online hits the inboxes of subscribers in the wood-to-energy sectors.
Subscribe/Renew
Wood Bioenergy is published and delivered worldwide 6 times per year. Free to qualified readers in the U.S. Subscribers outside the U.S. are asked to pay a small fee.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative.