Highland Pellets Remains Committed

Highland Pellets is revitalizing its wood pellet plant in Pine Bluff, Ark.
A recent advertisement promoting “Liquidation Sale, 4 Lines Available” with a photo that is the Highland Pellets wood pellet mill in Pine Bluff, Ark. has generated rumor that Highland Pellets is throwing in the towel.
Not true, says Highland Pellets Chairman Tom Reilley.
Earlier in the year Highland Pellets revealed it had temporarily shut down the plant because the drying technology installed had not met the company’s demands, and that the company was purchasing new equipment to be installed in 2020.
That remains the case, though the recent Liquidation Sale advertisement had some thinking that Highland had simply decided to give up the mill.
“As the old saying goes, ‘never let facts get in the way of a good story,” Reilley says.
Actually hitting on a link in the ad takes you to the Aaron Equipment web site, which explains the liquidation is tied to plant capacity upgrades. But sometimes people don’t hit the links.
“We are removing our green hammermills, drying systems, dry hammermills and rebuilding the heart of the plant with state-of-the-art equipment and hope to be back running and at a 12.5% increase in our name plate (600,000 MTPY) by the end of Q1 next year,” Reilley says.
Highland Pellets had partnered with Astec Industries for much of the operational works. The mill delivered its first pellets in April 2017 but has not gained traction. Astec Industries has since de-emphasized its wood pellet machinery business.
RELATED ARTICLES:
Latest news
Wood Pellet Mill In Adel Getting Closer
A proposed 450,000 metric tons per year industrial wood pellet mill to be built in Adel, Ga. is still an active project with nearly all of the pieces—including financing, equipment selection and air quality permit—in place, and construction expected to begin at mid-year 2022, according to Craig Whitlock, founder and…
Forest Service Backs Out Of Awarding Phase 2 Arizona Forests Restoration Contract; Uncertainties Persist For Novo Power
Anxious bidders for the Phase 2 contract that’s part of the federal 4 Forests Restoration Initiative (4FRI) seeking to treat and improve forest health conditions on more than 2.5 million acres across four Arizona national forests were told to wait a while longer after U.S. Forest Service (FS) officials abruptly…
Construction Ongoing At Drax Pellet Plants
Construction has started on Drax’s second satellite industrial wood pellet plant in Arkansas, this one in Russellville, Pope County, in northwestern Arkansas. Commercial operations are expected to begin at the plant in 2022. The move is part of a $40 million investment by Drax in the state…
Find Us On Social
Subscribe to Our Newsletter
Wood Bioenergy News Online hits the inboxes of subscribers in the wood-to-energy sectors.
Subscribe/Renew
Wood Bioenergy is published and delivered worldwide 6 times per year. Free to qualified readers in the U.S. Subscribers outside the U.S. are asked to pay a small fee.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative.