Drax Sets Sights On Carbon Capture

Bioenergy with Carbon Capture and Storage (BECCS) is an essential negative emissions technology needed for the UK to meet its legally binding net zero by 2050 target and demonstrate global climate leadership, according to UK power generator Drax Group. Work to build BECCS could get under way at Drax as soon as 2024, creating tens of thousands of jobs, supporting a post-COVID economic recovery, and capturing and storing up to 9 million tonnes of CO2 a year.

By 2027 Drax says its first BECCS unit could be operational, delivering the UK’s largest carbon capture project and permanently removing millions of tonnes of carbon dioxide from the atmosphere each year.

In order to deploy BECCS Drax must secure a Development Consent Order (DCO) from the government—a process that takes around two years to complete, and was slated to begin in March.

The first phase of the DCO application process includes an informal public consultation this spring. Earlier this year Drax sold its four gas power stations and announced it will not be progressing with plans to develop high efficiency gas power at the Drax site in North Yorkshire.

RELATED ARTICLES:

Drax Supports United Way’s Latest Efforts

Construction Ongoing At Drax Pellet Plants

Westervelt Sells Pellet Interests

Drax Announces $40M Investment In Arkansas

Pinnacle Renewable Energy To Be Acquired By Drax Group

Earthworm, Drax Working Together

Drax Adds Rail Link

Drax Can See End Of Coal Operations

Drax Appoints White To Lead U.S.

Latest news

Enviva Continues To Build Markets

In addition to 2,000,000 metric tons per year of long-term off-take contracts with Japanese counterparties, Enviva has recently executed several agreements with Japanese counterparties totaling more than 1,000,000 MTPY of additional volumes, including: —A 15-year,...

Strangers Scope Out Enviva

Enviva issued a statement that on August 20, the day of a public hearing concerning its plant at Northampton (Garysburg, NC,) two individuals claiming to be Danish reporters followed a logging truck from a job site around Clayton, NC to Enviva’s Sampson facility, some...

Germany Saying Goodbye to Coal

Germany Saying Goodbye to Coal Germany will shut down all 84 of its coal-fired power plants over the next 19 years (as of 2038) to meet its international commitments in the fight against climate change, the government’s Commission on Growth, Structural Change and...

Find Us On Social

Subscribe to Our Newsletter

Wood Bioenergy News Online hits the inboxes of subscribers in the wood-to-energy sectors.

Subscribe/Renew

Wood Bioenergy is published and delivered worldwide 6 times per year. Free to qualified readers in the U.S. Subscribers outside the U.S. are asked to pay a small fee.

Advertise

Complete the online form so we can direct you to the appropriate Sales Representative.