A one-year-old rail link has increased capacity to deliver more sustainable biomass from Drax’s LaSalle BioEnergy pellet plant in Urania, La., to its UK power station. The $15 million rail link, combined with other initiatives, have already contributed to a $5/tonne reduction in Drax’s biomass production costs in 2019.
The five miles of rail track connects Drax’s LaSalle BioEnergy pellet plant to the regional rail network, enabling freight trains to deliver the pellets to the company’s dedicated export facility at the Port of Greater Baton Rouge. The addition of the rail link has allowed Drax to deliver around 7,000 tonnes of sustainable biomass to the Port of Greater Baton Rouge in each train, compared to just 27 tonnes that could be transported by each truck previously.
A team of close to 40 contractors worked through two of the wettest Louisiana winters in decades to clear the site, excavating around 180,000 cubic yards of dirt to level off the ground and stabilize it before three sets of rail tracks could be laid. The work also included installing conveyors to get the pellets to the new rail loading point.
The rail link was commissioned last May and is now fully operational—and is part of Drax’s wider efforts to cut the costs of its biomass by around a third by 2027.
RELATED ARTICLES:
Drax Announces $40M Investment In Arkansas
Drax Sets Sights On Carbon Capture
Pinnacle Renewable Energy To Be Acquired By Drax Group
Earthworm, Drax Working Together
Latest news
New From Tigercat: 6040 Carbonizer
New From Tigercat: 6040 Carbonizer Tigercat Industries has announced the official release of its 6040 carbonizer—which replaces the 6050 carbonator that Tigercat marketed for a brief time after acquiring the product through the purchase of ROI in 2019. The mobile...
Michigan’s Viking Energy Biomass Plant Still Closing
Michigan’s Viking Energy Biomass Plant Still ClosingThe Viking Energy Biomass plant in Lincoln, Mich. is closing early despite being under contract until 2027 and a recent order not to let them out of the contract, according to reports. The company is moving ahead...
Novo BioPower Gets Some Breathing Room
Novo BioPower Gets Some Breathing Room Novo BioPower CEO Brad Worsley says the Salt River Project and Arizona Public Service have signed contracts through 2033 to buy electricity generated by burning biomass. Snowflake biomass plant is the only one in the state large...
Find Us On Social
Subscribe to Our Newsletter
Wood Bioenergy News Online hits the inboxes of subscribers in the wood-to-energy sectors.
Subscribe/Renew
Wood Bioenergy is published and delivered worldwide 6 times per year. Free to qualified readers in the U.S. Subscribers outside the U.S. are asked to pay a small fee.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative.