Active Energy Gears Up For CoalSwitch
Active Energy announced it has received its first order for its CoalSwitch pellet from PacifiCorp, the largest grid operator in the Western U.S. The product will be burned at PacifiCorp’s Hunter Power coal plant in Utah as part of a coal/biomass co-firing demonstration being conducted by PacifiCorp.
Active Energy says it will produce the pellets at its new operation in Lumberton, NC.
Active Energy will be supplying up to 900 tonnes for delivery by June 14, 2021.
Work on the CoalSwitch plant is ongoing, with construction activity expected to increase early in 2021. Active Energy appointed Player Design to complete the engineering and construction. AEG and Player Design anticipate the commissioning of the first CoalSwitch Plant in the second quarter.
“We are delighted to have received our first order of CoalSwitch from PacifiCorp,” comments Michael Rowan, CEO of Active Energy. “We are on track with our business plan and we are working at great pace to commission the plant.”
Active Energy Group plc is a London-listed renewable energy company that says it has developed a proprietary technology which transforms low-cost biomass material into high-value green fuels, and that its patented product CoalSwitch is the world’s only drop-in biomass fuel that can be mixed at any ratio with coal or completely replace coal in existing coal-fired power stations without requiring plant modification.
RELATED ARTICLES:
Latest news
Enviva Issues Statement Following Destructive Weather In Mississippi
Enviva Inc. has reported that all of its associates are safe and accounted for following a strong tornado that touched down in Amory, Miss., on March 24, 2023. The storm did, however, damage the company’s 115,000 metric ton per year wood pellet production facility, although Enviva’s larger plants and ports in…
Renova Delays New Biomass Plant Startup
Japan renewable power producer Renova Inc recently announced is postponing the launch of commercial operation of the 74.8-MW Tokushima-Tsuda biomass-fired power plant to some time in May 2023. Initially scheduled for a March 2023 startup, the plant is undergoing machine inspections, according to Renova…
Spectrum Moves Ahead At Adel
Spectrum Energy Georgia LLC plans to begin construction this summer of an industrial wood pellet facility in Adel, Ga. and expects to commission the plant 12 months later, or summer of 2024. The plant will operate at the site of an idled particleboard facility…
Find Us On Social
Subscribe to Our Newsletter
Wood Bioenergy News Online hits the inboxes of subscribers in the wood-to-energy sectors.
Subscribe/Renew
Wood Bioenergy is published and delivered worldwide 6 times per year. Free to qualified readers in the U.S. Subscribers outside the U.S. are asked to pay a small fee.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative.